Amirkabir Road Tunnel

This project is located in east of Tehran between Amin Hozur Street and Imam Ali highway. 4 km long Amir kabir tunnel was excavated by NATM method. Typical width of this tunnel is 20 m.

 

Amir Kabir Project Total Length: 4.060m
North Tunnel South Tunnel
Length (m) 2.700 1.360
Average Daily Traffic (ADT) 22.500 16.500
Design Speed 60 km/h 60 km/h
Overburden Max: 8.5 m Max: 8 m
Min: 4.5 m Min: 4.5 m
Shotcrete 45.000 m3
Excavation 357.000 m3
Concrete for Final Lining 90.000 m3