Amir Kabir Tunnel

Amir Kabir Tunnel

Employer: Tehran Engineering and Civil Engineering Organization

Advisor: Participation D2/P.O.R

Contractor: ERSA-Nimrokh Partnership

Project duration: 27 months

South tunnelNorth tunnelAmirkabir project
1616 (m)1567 (m)length
4650062500Average daily traffic
60 km/h60 km/hDesign speed
Maximum: 8 metersMaximum: 5.8 metersoverhead
Minimum: 4.5 metersMinimum: 4.5 meters
180000 m3Shotcrete
500000 m3Excavation
125000 m3Final coating of concrete

Project description:

The Amir Kabir Tunnel and Underpass is under construction in the east of Tehran Bazaar, between the intersection of Amin Huzoor and Imam Ali Highway. After passing under Shahrivar 17th Street and Shokoufeh Street, this tunnel reaches the Police Station Square and is divided into two branches, the northern and southern.

The northern tunnel along Darodian Street, as an east-west route from Imam Ali Highway towards Amin Huzoor, and the southern tunnel as a west-east route along Kerman Street, connect the aforementioned area to Imam Ali Highway.

Implementation of asphalt operations

Amirkabir Tunnel Shaft

The Embarkebir Tunnel has two shafts with a diameter of 10 meters, which are drilled using the NATM method. Shafts are drilled in horizontal and vertical stages. The depth of these shafts is 20 and 32 meters, and the thickness of their initial cover is calculated to be 30 centimeters and the thickness of the final cover is calculated to be 35 centimeters.

در خبرنامه ما عضو شوید تا در سریعترین زمان از جدیدترین اخبار ما مطلع شوید.

Related

اخبار مشابه و مرتبط با این خبر

South tunnelNorth tunnelNiayesh Tunnel Project2700 (m)2830 (m)length5250042000Average daily traffic80km/h80km/hDesign speedMaximum: 38 metersMaximum: 40 metersoverheadMinimum: 6 metersMinimum: 4.5 meters475000 m3Shotcrete1380000 m3Excavation265000 m3Final coating...

Leave a Reply

Your email address will not be published. Required fields are marked *